número de Presupuesto | 5074/19 |
fecha de Presupuesto | 25 septiembre, 2019 |
Total | €65.695,48 |
At.: Ryan Mobley
Replacemant of RTU's Centro - Oberhausen - OPTION B
Cantidad | Servicio | Tarifa/Precio | Subtotal |
---|---|---|---|
1 | LABOR | €0,00 | €0,00 |
8 hs. | Preparation and extracting refrigant removal exciting RTU's | €95,00 | €760,00 |
4 hs. | Dismantel and preparation electrical power supply RTU's | €95,00 | €380,00 |
8 hs. | Dismanteling of excisiting ductwork | €95,00 | €760,00 |
8 hs. | Disconneting RTU's from installations | €95,00 | €760,00 |
8 hs. | Disconneting RTU's from installations | €95,00 | €760,00 |
6 hs. | Adjustments steelconstruction footprint | €95,00 | €570,00 |
8 hs. | Placing and adjusting of new RTU's | €95,00 | €760,00 |
16hs. | Placing and mounting of new ductwork | €95,00 | €1.520,00 |
6 hs. | Adjustments and connection powersupplies | €95,00 | €570,00 |
6 hs. | Adjustments and connection supply hotwater coil | €95,00 | €570,00 |
8 | Support Blaich Automation (Daniel Kuttruff) on site with cables and hardware | €95,00 | €760,00 |
1 | MATERIALS | €0,00 | €0,00 |
25,6 KG | Disposal refrigant 410A | €17,25 | €441,60 |
12 pc | Mountings | €69,00 | €828,00 |
14 m | Steel support beams | €80,50 | €1.127,00 |
6 pc | Tower Crane | €517,50 | €3.105,00 |
2 pc | Ductwork RTU1 & RTU2 | €1.265,00 | €2.530,00 |
2 pc | Isolation of ductwork and Stucco plate finishing | €1.725,00 | €3.450,00 |
2 pc | Electrical cabels ans materials | €201,25 | €402,50 |
2 pc | Piping hotwater supply, appendages | €115,00 | €230,00 |
2 pc | Isolation of hotwater piping and Stucco plate finishing | €230,00 | €460,00 |
1 pc | Small materials | €175,50 | €175,50 |
1 | RTU | €0,00 | €0,00 |
1 pc | DAIKIN, model UATYQ75AFC2Y1 - Size (mm) 1800x3750x2240; weight (kg): 1553 | €28.720,73 | €28.720,73 |
1 pc | DAIKIN, model UATYQ30AFC2Y1 - Size (mm) 2150x1790x1730; weight (kg): 780 | €16.055,15 | €16.055,15 |
Subtotal | €65.695,48 |
IVA | €0,00 |
Total | €65.695,48 |